| |
News on Ports
Major
ports efficiency level improves The
average pre-berthing waiting time at major ports has declined
from 0.9 days in 1999-2000 to 0.5 days in 2000-01, while the average
turn-around time of ships has touched 4.1 from 5.1 days in the
same period. The improvements in efficiency parameters have been
possible through creation of additional cargo handling capacity
at major ports. The total cargo handling capacity at the major
ports went up from 219.55 million tonnes at the beginning of Ninth
five-year plan as on April 1, 1997 to 291.45 million tonnes on
March 31 2001. The total capacity at major ports is expected to
touch 344.40 million tonnes by March 31 2002, the terminal year
of the plan. The total capacity additions at major ports during
the Ninth plan period works out to 124.85 million tonnes.
JM
Baxi-Dubai Port Authority consortium bags contract for VPT box
terminal JM Baxi-Dubai Ports Authority consortium has bagged
the contract for operating and managing the container terminal
at the Vishakapatanam Port. The consortium was the highest bidder
for the project and was has been selected by the Ministry of Shipping.
The consortium had reportedly quoted an upfront fee of Rs. 3 crore
and a royalty worth Rs. 29 crore during the concession period
of 30 years. The outer berth developed by VPT at a cost of Rs.59
crore will be entrusted to the private operator for being converted
into a multi-purpose berth, including container handling facilities.
VPT
meets the targets set for cargo traffic The Vishakhapatnam
Port Trust (VPT) has achieved the cargo traffic during the financial
year 2000-01 by handling 42.5 million tonnes of cargo traffic,
against the target of 42.5 million tonnes set by the Ministry
of Shipping (MoS). The traffic in respect of POL, thermal coal
and lamp coke has exceeded the target. However, there is a marginal
shortfall was seen in respect of iron ore, due to global economic
recession and in fertilizers and raw materials. The port handled
17.84 million tonnes of POL, exceeding the target of 15.50 million
tonnes, while 3.80 million tonnes of thermal coal was handled
against target of 3.60 million tonnes. The port also handled 5.8
million tonnes of coking coal and lamp coke against a target of
5.2 million tonnes. In the fiscal year 2002-03, the port is expected
to handle a total traffic of 44.5-million tonnes.
JNPT
records 1.5 million containers Jawaharlal Nehru Port Trust
(JNPT) has achieved a traffic level of 1.5 million containers
during the year 2000-01, exceeding the target of 1.35 million
containers fixed by the Ministry of Shipping (MoS) during the
year. The port has also exceeded the target of 0.30 million tonnes
set for dry bulk (comprising fertilizer and foodgrains) traffic
by handling at 0.36 million tonnes of dry bulk cargo, as on March
18 2002. The port has, however, fallen short of the target set
by MoS in respect of liquid and general cargo handled at 3.34
million tonnes and 0.86 million tonnes respectively. The actual
volume of liquid and general cargo handled at the port stood at
2.88 million tonnes and 0.78 million tonnes respectively. Meanwhile,
the NSICT which manages the two container terminals at the port
has reported 36.71 per cent growth to 8,53786 teus during April-February
2000-01 as compared to 6,24,531 teus I the corresponding period
of the previous financial year. The JNPT, which manages three
of the container terminals, in the same period handled 5,61,304
teus against 4,48,602 teus in the same period of previous year.
TAMP
to be made appellate tribunal The Union Shipping Ministry
is reportedly working on a proposal to convert the Tariff Authority
for Major Ports (TAMP) into an appellate tribunal. Under the proposal
, the port service providers can independently fix and revise
tariffs without seeking TAMP approval. However, port users can
approach the appellate tribunal for any grievances relating to
tariffs fixed by the service providers. The plan to convert TAMP
into a tribunal was first mooted by a committee under Mr.C. Babu
Rajeev, formerly chairman of Kochi Port Trust (KPT), which went
into modalities of over-hauling the Major Ports Trust Act, 1963
and the Indian Ports Act 1908. While approving amendments to the
MPT Act earlier for creating TAMP, the government had fixed an
initial time-frame of five year tenure, based on the premise that
a tariff regulator would be necessary till market forces came
into play to fix and revise tariffs at major ports. The government
now feels that sufficient competition has been generated in major
ports and port operators can now independently fix the tariffs,
while TAMP can withdraw into a adjudicating role.
Fresh
tender likely for Hooghly estuary works The
Kolkata Port Trust (KoPT) is reportedly considering floating a
fresh tender for the River Regulatory Scheme for improving the
draft level in Hooghly estuary. While several international dredging
contractors had submitted their bids in response to the tender
floated early this year, none of the bidders have been found to
be fulfilling the conditions stipulated in the original tender.
The stipulation in the tender required that successful contractor
must have taken up at least Rs 10-crore worth of work experience,
in building dykes with geo-tubes. However, none of the bidders
for the dredging contracts fulfilled the condition. Since most
international contractors have already bid for the work, the port
authorities, are likely to relax certain conditions stipulated
in the original tender, when the bid is re-floated.
Back
to top
News on Shipping
Essar
Shipping promoters to hike their stake to 74 per cent The
promoters of Essar Shipping have decided to hike their stake in
the company to 74.39 per cent from existing 48.34 per cent, following
the proposed issue of equity shares by appropriation of un-secured
interest-free loan (quasi equity). A notice calling for extra-ordinary
general meeting says that 10:50 crore equity shares would be issued
at par, in lieu of unsecured interest-free loan of Rs. 105 crore,
while Rs. 9.50 crore equity shares will be issued, as fresh equity
shares at par to raise Rs. 95 crore, to be used to augment the
long term requirements of the company. The proposed move apart
from increasing the stake of the promoters, would also benefit
the company in bringing down the tax liability, following the
broadening of the definition of Section 33AC to allow greater
amount to be transferred to tax-free ship acquisition reserves.
The conversion of debt to equity would result in increased net
worth for Essar Shipping, thereby enabling it to transfer more
amounts into ship acquisition reserve and reduce its tax liability.
CBEC
allows overseas bound Indian ships to carry coastal cargo The
Central Board of Excise and Customs (CBEC) has issued a notification
allowing ocean-going Indian registered ships, operating in routes
covering more than one Indian port to a port outside India and
vice versa, to carry coastal containers along with export-import
cargo between two Indian ports. The CBEC move will help create
better capacity utilization of ships and bring down the transaction
cost of exports and imports. Hitherto, this facility was not available
for ocean-bound vessels. The CBEC decision will benefit Shipping
Corporation of India (SCI), which has a strong presence in coastal
cargo movements.
Lots
Shipping launches its second cargo barge Lots Shipping
and Trading Private Limited, a Kochi-based barge operator has
launched its second cargo-cum-container barge Muziris
to be deployed in the West Coast Canal, part of the National Waterways
No- 3 in Kerala. Gentech Marine Engineers, a Kochi-based yard
built the 350-tonne barge was built in 79 days at a total coast
of Rs.0.75 million. The first vessel of the company, Meenachil,
a 550-tonne barge is currently transporting sulphur and rock phosphate
for the public sector FACT from Cochin Port Trust (CPT).
Back to top
News on Shipyards
MoS
to consider CSL proposal for expansion The Ministry of Shipping
is reportedly considering a proposal submitted by Cochin Shipyard
Ltd. to expand the ship repair facilities at an estimated cost
of Rs.98.38 crore. The expansion plan envisages installation
of 120 metre ship lift system with essential facilities for
which CSL would contribute Rs 48.38 crore from its internal
resources, while balance Rs.50 crore is expected to be raised
from the market. Singapores Keppel Shipyard is believed
to be interested in forging a joint venture with CSL for setting
up ship repair facilities.
Cochin
Shipyard to construct fire-fighting vessel for VPT
Cochin Shipyard Ltd. (CSL) has formally laid the
keel of the Fire Float built for Vishakapatanam Port Trust (VPT).
The order for the design, construction and delivery of the special-purpose
vessel was bagged by CSL against stiff competition. The 32.9
metre long vessel, which will have a breadth of 10 metres and
a depth of 4.25 metres, with a crew capacity of 10, will cost
of Rs.7.59 crore. The fire fighting and rescue vessel will be
delivered by June 2003. Apart from this, the CSL is also constructing
a ocean-going trailing suction hopper dredger for Chennai Port
Trust (CPT) and another 93,000 dwt double hull tanker MT Maharshi
Parashuram for Shipping Corporation of India (SCI). The public
sector shipyard is also constructing a 130 metre-long barge
for National Petroleum Construction Company, Abu Dhabi, which
it won against stiff competition from yards in Singapore and
China.
|
|